The company recognized for its skills in Project Management, consistency in quality, implementation and completion ofprojects ahead of the time schedule.

Construction and Site Development of OMNICO Concrete Batching Plant
- Client: OMNICO Consortium Inc./ William Uy Const. Corp.
- Date Awarded/ Completed:July 2004 – July 2005

Construction of Equipment Shelter, Shades and Water Treatment Facility Shelter at Bacoor, Cavite Stockyard
- Client: William Uy Construction Corporation
- Date Awarded/ Completed:April 2003 – July 2003

Metro Manila Skyway Project
- Client/ Contractor: CITRA/ TRA Hutama-RSEA J.O. Inc.
- Date Awarded/ Completed:June 1998 – September 1998
- Works done: Fabrication and Installation of Rebars

Sta. Rita Calaca 230KV Transmission Line Project
- Client: First Gas Power Holdings/ MIESCOR
- Date Awarded/ Completed: December 1997 – June 1998
- Works done: Riverbank Erosion Protection at Tower 96 and Tower 130

50 Meters Microwave Tower at Dingle Substation, Iloilo
- Client:NGCP
- Date Awarded/ Completed: October 2009 – February 2010
- Works done: Design, Supply, Fabrication, Delivery, Galvanizing and Erection of tower