Loading...
Alt

Western Luzon 500KV Backbone Project Stage I: Balsik (Hermosa) – Castillejos 500 KV Transmission Line Project

  • Client: NGCP (National Grid Corporation of the Philippines)
  • Date Awarded: November 8, 2017
  • Status: On-going (6%)
  • Tower Foundation, Erection of Towers and Stringing Works