Loading...

SMSF Community Library (2-Storey Building)

  • Client: Salustiano Mejes Sr. Foundation Inc.
  • Date Awarded/ Completed: April 2011 – August 2014
  • Works done: Building Construction

Santiago – Tuguegarao 230KV Line 2 Transmission Line Project

  • Client/ Contractor: NGCP/ TBEA Shenyang Transformer Group Co. Ltd.
  • Date Awarded:/ Completed: November 14, 2013 – September 15, 2017
  • Works done: Civil, Erection, Stringing, Testing & Commissioning and Slope Protection

5 Unit, 2-Storey Residence with Warehouse and Employee Quarters

  • Client: TBDC
  • Date Awarded/ Completed: March 2011 – October 2011
  • Works done: Building Construction

Lumban EHV – Bay 230KV Transmission Line Upgrading Project

  • Client/ Contractor: NGCP/ TBEA Philippines International Power Engineering, Inc
  • Date Awarded/ Completed: July 2, 2012 – September 11, 2016
  • Works done: Civil, Erection, Stringing, Testing & Commissioning and Slope Protection

Upgrading of Panit-an – Nabas 138KV Transmission Line Project

  • Client/ Contractor: NGCP/ China CAMCE Engineering Co., Ltd.
  • Date Awarded/ Completed: March 30, 2016 – March 26, 2017
  • Works done: Civil, Erection, Stringing, Slope Protection Works, Testing and Commissioning

Concepcion 135MW CFBC Coal Fired Power Plant – Transmission Line Portion

  • Client/ Contractor: Palm Concepcion Power Corporation/ TBEA Philippines International Power Engineering, Inc.
  • Date Awarded/ Completed: May 26, 2015 – January 31, 2016
  • Works done: Civil, Erection, Stringing and Slope Protection Works

Southern Panay Backbone 138KV Transmission Line Project – SCH III

  • Client/ Contractor: NGCP/ TBEA Shenyang Transformer Group Co. Ltd.
  • Date Awarded/ Completed: April 2011 – July 2012
  • Works done: Civil, Erection, Stringing, Testing & Commissioning, Slope Protection, Demolition/ Retrofitting, Fabrication and Segregation

Mariveles Transmission Reinforcement Project

  • Client/ Contractor: NGCP/ China National Electric Engineering Co., Ltd.
  • Date Awarded/ Completed: September 2011 – December 2011
  • Status: Completed
  • Work done: Reconductoring of Limay – Hermosa T/L