230KV Transmission Line By-Pass Structures affected by Typhoon Reming

  • Client/ Contractor: TransCo/ Kalpataru
  • Date Awarded/ Completed: April 2007 – April 2008
  • Works done: Dismantling, Retiring and Hauling
Alt

Batangas – Makban 230KV Transmission Line Project – BTRP SCH II

  • Client/ Contractor: TransCo/ AER
  • Date Awarded/ Completed: October 2007 – December 2007
  • Works done: Tower Erection – 6 Towers and Uplifting of Span BM- 24
Alt

69KV Steel Poles of Temporary By-Pass for Tower 99-102 of Naga-Daraga T/L

  • Client/ Contractor: TransCo/ FABMIK
  • Date Awarded / Completed: October 2007 – November 2007
  • Works done: Construction and Erection of Steel Poles (58 Poles – 6KM)
Alt

69KV Steel Poles of Temporary By-Pass for Tower 19-23 of Bacman-Daraga T/L

  • Client/ Contractor: TransCo/ FABMIK
  • Date Awarded/ Completed: October 2007 – November 2007
  • Works done: Construction and Erection of Steel Poles (34 Poles – 2.7KM)
Alt

Reconstruction of Damaged ACSR at Plant D Tie Line including Splicing and Clipping of Jumper

  • Client: Laguna International Industrial Park Association, Inc.
  • Date Awarded/ Completed: April 2007 – August 2007