The company recognized for its skills in Project Management, consistency in quality, implementation and completion ofprojects ahead of the time schedule.
230KV Transmission Line By-Pass Structures affected by Typhoon Reming
- Client/ Contractor: TransCo/ Kalpataru
- Date Awarded/ Completed: April 2007 – April 2008
- Works done: Dismantling, Retiring and Hauling
Batangas – Makban 230KV Transmission Line Project – BTRP SCH II
- Client/ Contractor: TransCo/ AER
- Date Awarded/ Completed: October 2007 – December 2007
- Works done: Tower Erection – 6 Towers and Uplifting of Span BM- 24
69KV Steel Poles of Temporary By-Pass for Tower 99-102 of Naga-Daraga T/L
- Client/ Contractor: TransCo/ FABMIK
- Date Awarded / Completed: October 2007 – November 2007
- Works done: Construction and Erection of Steel Poles (58 Poles – 6KM)
69KV Steel Poles of Temporary By-Pass for Tower 19-23 of Bacman-Daraga T/L
- Client/ Contractor: TransCo/ FABMIK
- Date Awarded/ Completed: October 2007 – November 2007
- Works done: Construction and Erection of Steel Poles (34 Poles – 2.7KM)
Reconstruction of Damaged ACSR at Plant D Tie Line including Splicing and Clipping of Jumper
- Client: Laguna International Industrial Park Association, Inc.
- Date Awarded/ Completed: April 2007 – August 2007