Mariveles Transmission Reinforcement Project

  • Client/ Contractor: NGCP/ China National Electric Engineering Co., Ltd.
  • Date Awarded/ Completed: September 2011 – December 2011
  • Status: Completed
  • Work done: Reconductoring of Limay – Hermosa T/L
Alt

Negros – Panay Interconnecting Transmission Line Project

  • Client/ Contractor: NGCP/ Zhejiang Electric Transmission & Transformation Engineering Corp.
  • Date Awarded/ Completed: June 2011 – December 2011
  • Works done: Stringing Works
Alt

Northern Panay 138KV Transmission Line Backbone Project – SCH II

  • Client/ Contractor: TransCo/ Hyundai Engineering Ltd., Inc.
  • Date Awarded/ Completed: October 2008 – January 2011
  • Works done: Civil, Erection, Stringing, Slope Protection, Riverbank Protection, Cut-in Lines, Installation of Barbed Wire Fence at Nabas S/S
Alt

Northern Panay Backbone Project at Panayakan, Tangalan and Regador, Ibajay, Aklan

  • Client: NGCP
  • Date Awarded/ Completed: May 2010 – June 2010
  • Works done: Clearing Works
Alt

Tiwi Plant, Naga-Daraga and Bacon-Daraga 230KV T/L

  • Client/ Contractor: TransCo/ Kalpataru – AER
  • Date Awarded/ Completed: June 2007 – May 2008
  • Works done: Installation of Steel Towers and Line Materials for the Typhoon damaged portion