Replacement of 48 Wood Poles to Steel Poles for 3 Repeater Station at Cuyapao R/S, Dasol R/S and San Isidro R/S
- Client: NGCP
- Date Awarded/ Completed: February 2010 – May 2010
Construction of Power Supply Line for New Bacman Repeater Station
- Client: TransCo
- Date Awarded/ Completed: August 2008 – Demcember 2008
Construction of Perimeter Fence for 8 Repeater Stations
- Client: TransCo
- Date Awarded/ Completed: August 2008 - December 2008
Waterproofing of 6 Repeater Stations
- Client: TransCo
- Date Awarded/ Completed: July 2008 – November 2008
Supply and Delivery of Elliptical Waveguide
- Client:TransCo/NGCP